BHP Iron Ore Case Study 3

30 MW POWER STATION AT 33 KV

Home   Projects BHP Iron Ore Case Study 3 | UON, Perth

BACKGROUND

UON were tasked with delivering a 30MW Power Station and electrical distribution power at 33kV. The Power Station was required to sustain operations during the relocation of a 132kV transmission line. The whole shutdown and operation was dependent on the successful energization of the power station on-time which was achieved. The project was designed and installed within the 12-week timeline.

0

Team members

Pilbara

Region

0

Pieces of equipment

BHP

Client

0

Hours worked LTI-free

Iron Ore

Commodity

0 MW 

Scale of project 

Rental

Contract

KEY SUCCESS

The key success of the Rapid-Deployment 30MW / 33kV Power Station was UON’s time management and orchestrated scheduling of people and plant. This allowed UON to deliver on time and without incident. UON’s close working relationship with the client on site allowed for a smooth deployment and synchronization of resources.



DELIVERABLES

  • 20 Modular Diesel Generators
  • 5 Modular 415V/33kV Substations
  • 33kV Switch Room
  • 440kL Fuel Storage
  • Unloading facility and Powerline Interconnection
  • All design, construction, commissioning, operation and decommissioning
  • Full design and construction delivered within the 12-week timeline

Other Projects

BHP Iron Ore Case Study 1

Major Water Infrastructure

Adaman Gold Case Study 1

Supply and Construction of Open Pit Dewatering of 7 Billion Litres

Novo Gold Case Study 1

Supply and Installation of Power Station for Underground Mining

Rio Tinto Iron Ore Case Study 1

Water Management Infrastructure

Rio Tinto Iron Ore Case Study 2

Design Construct Major Dewatering Infrastructure

BHP Iron Ore Case Study 2

Water Management Infrastructure

Get A Prompt Response