BHP IRON ORE CASE STUDY 1

Water Management Infrastructure

BACKGROUND

UON was engaged as the head contractor to Design, Supply, Install and Commission thirteen downhole bore packages, Generator & Headworks Trailers, Fuel Tanks and associated equipment including UON’s (Patent Pending) PROPOWER™ GMC Generator Technology. Construction works on this project were completed with RSK Contracting.

Team Members

Pieces of equipment

Hours worked LTI-free

Pilbara

Region

BHP

Client

IRON ORE

Commodity

PURCHASE

Contract

KEY SUCCESS

UON minimised the loss of dewatering across the BHP sites during the removal of existing infrastructure and replacement with new infrastructure. This project required a high level of planning from our Projects and Production & Fabrication Facilities. UON achieved this safely and on time with zero recordable incidents for the duration of the project.

DELIVERABLES

    • 11 x 300kvA GMC Generator on Trailer
    • 4 x 200kvA UON GMC Generator on Trailer
    • 6 x 250kvA UON GMC Generator on Trailer
    • 3 x 150kvA UON GMC Generator on Trailer
    • 18 x 4000L UON Fuel Tanks
    • 16 x 92 to132kW Downhole Bore Pump Packages
    • 6km of HDPE
    • Steel Manifold Pipework and Valves
    • Hydro Testing, Installation & Commissioning
    • Delivered On-Time and In-Budget

    OTHER PROJECTS

    Dacian Gold Case Study 1

    Dacian Gold Case Study 1

    The key success of the rapid-deployment 6 MW / 11 kV power station was the modularization and flexibility of all equipment provided as part of UON’s complete solution

    Bellevue Gold Case Study 1

    Bellevue Gold Case Study 1

    UON were tasked with delivering a dewatering solution for an old mine being reactivated, via an existing ventilation shaft.

    Adaman Gold Case Study 1

    Adaman Gold Case Study 1

    UON was contracted to design, manufacture and install a pontoon system to dewater over 7 Billion litres from an old open pit mine.

    BHP Case Study 3

    BHP Case Study 3

    The key success of the Rapid-Deployment 30MW Power Station was UON’s time management and orchestrated scheduling of people and plant.

    GET A PROMPT RESPONSE

    "*" indicates required fields