Rapid-Deployment 30MW Power Station

UON were tasked with delivering a 30MW Power Station and electrical distribution power at 33kV with a small catch – the team was given 12 weeks to design and construct the station with no movement on the end date for power turn-on. The Power Station was required to sustain operations during the relocation of a 132kV transmission line. The whole shutdown and operation was dependent on the successful energization of the power station on-time.

Project Name

Rapid-Deployment 30MW Power Station

Project Value

Not disclosed

Location

North-West Pilbara Region, Western Australia

Duration

May 2016 - September 2016

Summary

Install and Commission a 30MW Power Station and Electrical Distribution Power at 33kV within 12 weeks

Background Information

UON were tasked with delivering a 30MW Power Station and electrical distribution power at 33kV with a small catch – the team was given 12 weeks to design and construct the station with no movement on the end date for power turn-on. The Power Station was required to sustain operations during the relocation of a 132kV transmission line. The whole shutdown and operation was dependent on the successful energization of the power station on-time.

Key Success

The key success of the Rapid-Deployment 30MW Power Station was UON’s time management and orchestrated scheduling of people and plant. This allowed UON to deliver on time and without incident. UON’s close working relationship with the client on site allowed for a smooth deployment and synchronization of resources.

Equipment:

  • 20 Modular Diesel Generators
  • 10 Modular 415V/33kV Substations
  • 33kV Switch Room
  • 440kL Fuel Storage
  • Unloading facility and Powerline Interconnection
  • All design, construction, commissioning, operation and decommissioning
 